February Update!

An update from Chair of The Greig Hall Working Group, 27th Feb 2022

Last week was a significant week for the hall!

Sunday the 20th February

We held a volunteers coffee morning which gave our volunteers the opportunity to have look at the hall, chat to the members of the working group and sign up to a particular area of work. We have a fantastic bunch of volunteers (and more signed up on the day!) although frustratingly, we have not been able to use their skills and energies before now. This delay is due to the heating system talking longer to both specify and tender. The replies came back last week and we will be assessing the bids this coming week. This delay has unfortunately set the electrical work back as well, however we hope to catch up soon.

Monday 21st February

The ceilings started coming down in the main hall. The reason for doing this is to inspect the roof, install insulation (none before) and install electrical wiring (heating, lighting) and piping for the heating system. When all that work is complete, including the heating system blowers framework, a new ceiling will be installed that is slightly lower than that previously.

Alcester Town Council have applied for a £100k loan to help complete the work as quickly as possible. This should enable the hall to be functionally open in September and we are already planning the first performances and engagements.

Thursday 24th February

The ceiling is down and the rails for the new insulation are going on. Today also saw the first of the old radiators being removed from the lounge. This will release valuable floor space in the room.

You can see some of the photos from this week’s work below, and we’ll provide more updates as it progresses!

Cllr. Mark Cargill, Chair Greig Hall Working Group

February Update

An update from Chair of The Greig Hall Working Group, 27th Feb 2022 Last week was a significant week for the hall! Sunday the 20th February We held a volunteers coffee morning which gave our volunteers the opportunity to have look at the hall, chat to the members of...

read more

Christmas Fayre

An update from Chair of The Greig Hall Working Group, 24th Dec 2021 The Christmas Fayre on the 4th December was a huge success and thank you to the hundreds of people who came along to see us. I’m delighted to say that we raised over £2,000 for the restoration fund,...

read more

Lots of Fundraising!

An update from Chair of The Greig Hall Working Group, Cllr. Mark Cargill. Work has now started on the roof to make it weather tight for winter. The work involves replacing broken tiles, repairing the gutters, fixing the burnt areas on the roof (yes, someone was having...

read more

Work on the roof has begun!

An update from Chair of The Greig Hall Working Group, Cllr. Mark Cargill.We are finally starting to see the real beginning of the refurbishment of the hall with work starting on the roof. These repairs were prioritised as the roof is the most important part of any...

read more

Clearing Out

An update from Chair of The Greig Hall Working Group, Cllr. Mark Cargill. Today we had the hall cleared of all the rubbish left behind after being handed over. A great deal of what was left is rubbish, but where possible items of value have been sent to a recycling...

read more

Inside The Greig Hall

The Greig Hall's doors closed in 2011 and over the last 10 years barely anyone has stepped inside. When we received the keys we were curious as to the state of the Hall and the amount of work that would need to be done. This video shows you what we found and gives you...

read more

The Greig Hall Is Back!

What a week! After several safety checks and sign off from the Energy Performance Certificate (after a last minute scramble for some energy efficient light bulbs!) Stratford District Council were able to complete the lease of the Greig Hall to Alcester Town Council....

read more